Transportation Engineering

Transportation Engineering

Badger Creek (Rugg Road) Culvert Repair

Project description

Status

Planning

Updated: Nov. 28, 2023

Replace two metal culverts carrying Badger Creek under Rugg Road with a larger, fish-friendly culvert near the Springwater Corridor Trail and the Telford Road intersection in the Boring area.

Why

To preserve the roadway, allow for proper drainage, and assure safe passage for travelers. This project will also provide improved fish passage conditions to allow salmon and other migratory species to pass upstream into coolwater habitat.

Schedule

  • Design: April 2021 to Winter 2024
  • Right of way: December 2022 - Spring 2025
  • Construction: Summer 2025 - Winter 2025

Traffic impact

  • A road closure may be needed during construction. Project is expected to take up to 2 months to complete.
  • Site work limited to a state approved in-water work window period of June 1-Sept 30

Current activities

  • Project in planning phase
  • Acquisition of all required permits and approvals from local, state and federal regulatory agencies

Funding

  • Project estimate $635,000
  • Funding is provided from county road funds
Contact
Department Staff
Devin Patterson
503-742-4666
 
Sidebar Heading
Related Information
New Format?
Off

Walk Bike Clackamas Plan: Improving walking and biking for everyone

The goal of the Walk Bike Clackamas Plan is to create a comprehensive, long-term vision to improve opportunities for people walking and biking as they travel in the county.

Review the draft Walk Bike Plan 

What will the plan do?

The plan will:

  • Establish infrastructure priorities, such as where to build new bike lanes and sidewalks, which will help the county apply for future grants and other funding opportunities. 
  • Identify programs that increase safety and convenience of walking and biking (like Safe Routes to School).
  • Update active transportation polices and adopt performance measures so we can track progress during implementation
  • Serve as the pedestrian and bicycle transportation elements of the county’s updated Transportation System Plan (TSP)

Project area

The project applies to all urban and rural unincorporated areas of Clackamas County, and will coordinate with cities in the county. 

Key Terms and Definitions

The following key terms are central to understanding Walk Bike Clackamas:

  • Active transportation: human-powered modes of travel, including walking, rolling a wheelchair, and riding a bicycle.
  • Facilities and infrastructure: designated places for people to walk, roll, and ride a bike, such as off-street shared-use trails, painted bike lanes on streets, marked and signalized crosswalks, and sidewalks and multiuse paths.
  • Equity: reducing or eliminating disparities by thoughtfully spreading resources to overcome the unique barriers different groups face.
  • Health equity: providing fair access to opportunities and resources for people to achieve physical and social health and well-being, and reducing barriers caused by circumstances outside of a person’s control, such as race, ethnicity, or social background.
  • Communities of interest: groups of people who have experienced or continue to experience inequitable access to resources in society. Walk Bike Clackamas is focusing on achieving equitable outcomes for the following communities of interest:
    • Black people, Indigenous people, and People of Color (BIPOC)
    • Immigrants
    • People with limited English proficiency
    • Low-income and low-wealth community members
    • Low- and moderate-income renters and homeowners
    • People with disabilities
    • Youth and seniors

Timeline

WB Timeline

Walk Bike Advisory Committee (WBAC)

Community members and technical experts will review project work and advise the project team. Meetings are open to the public and include time for public comment.

Name of View
No results were found for your search. Please try again.

WBAC Members

NameOrganization/Area/Expertise
Jacob AndersonSocial/Environmental Justice
Dean ApostolRural Interests
Mark BentzClimate Action
Allina CannadyPublic Health
Mike CardwellBicyclists
Joseph EdgePedestrian/Bikeway Advisory Committee
Josh FisherMobility Needs
Kevin HaroDiversity
Sandra HendersonPedestrians
Kymberly KaluBike commuting/e-bikes
Aaron LiersemanTourism
Natasha MuroTransit
Jay PanagosBicyclist/Safety
Nicole PerrySafe Routes to School
Rob SadowskyVision Zero
Christian SnuffinTraffic engineering
Tonia WilliamsomTrails
Marika YumangHealth
Staff
Scott HoelscherProject Manager
Brett SetterfieldTransportation Planner
Ellen RogalinCommunity Involvement

Why do we need a new plan?

  • Things have changed
    Since the last update in 2003, our transportation system has drastically changed. Projects have been built and policy priorities are different.
  • Oregon law
    State requires counties to develop balanced transportation systems and regularly update their bicycle and pedestrian plans.
  • Climate goals
    The Board of County Commissioners has set a goal for the county to be carbon neutral by 2050, which means balancing our greenhouse gas emissions to capture as much as we emit. Updating our Pedestrian and Bicycle Master Plan will help reach this goal.
  • New mobility options
    Planning for opportunities like bike share, e-bikes, cargo bikes and other advancements were not included in the last plan. To increase accessibility and safety in Clackamas County, emerging technologies could be integrated into our multi-modal transportation system.

Sign up for email updates

 
Contact
Department Staff
Scott Hoelscher
Senior Planner – Multimodal Transportation
503-742-4533
Sidebar Heading
Related Information
New Format?
On

Molalla River (Knights Bridge Road) Bridge Repairs

The Molalla River (Knights Bridge Road) Bridge in the Canby area is an important connection for delivery of goods and services throughout the region. Bridge repairs will include painting, sealing cracks on the deck, resurfacing the deck, and repairing the concrete columns and bridge approaches. This project also includes seismic upgrades. 

Status

Design phase

Updated: Dec. 21, 2023

Why

To preserve and extend the life of the bridge, to remove weight restrictions, allow for traffic to cross in an emergency, and to improve resiliency within our essential transportation network in the event of an earthquake.

Schedule

The schedule has been delayed by one year due to environmental permitting requirements and scheduling conflicts. 

  • Design: May 2022 to March 2023
  • Right of way: April 2023 to Spring 2024
  • Construction: Summer 2025 to Summer 2026

Traffic impacts

Single-lane closures will be needed during inspection and design phase. A four-month full road closure on N Knights Bridge Road at the bridge site is anticipated to pave the deck and perform bridge repairs. 

Current activities

Design by Consor/Quincey Engineering has progressed to 60% and is awaiting review by environmental agencies for permit applications. Project advertising is anticipated to be bid in Oct. 2023. 

Funding

  • Project estimate $5.4 million
  • Funding is provided from ODOT Local Bridge Program with a 10.3% match from County Road Funds 
 
Contact
Department Staff
Stan Monte
Construction Project Manager
503-742-4678
Sidebar Heading
Related Information
New Format?
Off

Hideaway Court Culvert Replacement

In early 2021, heavy rains and strong winds caused fallen trees in Johnson Creek to damage the culvert supporting the road on Hideaway Court, in the Damascus and Boring areas. A temporary bridge is in use until the culvert can be replaced.

The culvert will be replaced with a bottomless culvert to allow for safe fish passage. 

Status

Design phase

Updated: March 17, 2023

Why

To preserve residential access.

Schedule

The county began the design phase in April 2021. Construction is planned between July and Aug. 2023, during daytime hours. Work will take up to 5 weeks to complete.

Traffic impacts

Single-lane closures will be needed during construction.

Current activities

Waiting for final design plans. Will send out construction bid by March 2023.  

Funding

  • Project estimate $950,000
  • Funding is provided from Damascus County Road Funds
Contact
Department Staff
Stan Monte
Construction Project Manager
503-742-4678
Sidebar Heading
Related Information
New Format?
On

Rugg Road Landslide Repairs

In early 2021, heavy rains and strong winds toppled trees, causing the slope to collapse next to Rugg Road near the Hideaway Court intersection in the Damascus area. A retaining wall will be built at this location.

Temporary protective sheeting and plant seeding are in place until permanent repairs are constructed.

Status

Construction phase

Updated: July 18, 2024

Why

To stabilize the slope next to Rugg Road.

Schedule

  • Design: March 2021 - March 2022
  • Construction: July 2024 - Oct. 2024

Traffic impacts

Building the retaining wall will require two temporary road closures. Rugg Road will close for 4 weeks to place the anchors and construct the wall facing. The road will then open to traffic for 3-4 weeks for the wall to settle properly. After this, the road will close for another 4 weeks to construct the final roadbed, add guardrail and pave the road.

Road closures are needed for the majority of construction. While the road closure schedule may need to be adjusted, the tentative plan is:  

  • Road closed: July 8th to Aug. 11 
  • Road open: Aug. 12 to Sept. 18 
  • Road closed: Sept. 19 to Oct. 17

When a road closure is not necessary for construction, expect shoulder and lane closures with flaggers guiding vehicles daily through the work zone between 7 a.m. to 6 p.m., Monday through Friday. While we do not expect any weekend work, it may be needed depending on many factors. Local access to driveways will be maintained. Pedestrian access will be provided.
 

Current activities

Construction phase

Funding

  • Project estimate $970,000
  • Funding is provided from Damascus road funds

Stay In Touch

 
Sidebar Heading
Related Information
New Format?
On

Canby Ferry Intelligent Transportation System Project

This technology infrastructure project will help connect ferry riders with information on the operating status of the ferry.

Status: Construction

Updated: June 25, 2024

The project includes:

  • Extending fiber optic cable to the ferry location to provide wireless connection to electronic signs
  • Adding cameras at the ferry landings for images to be viewed on the website and ODOT TripCheck
  • Upgrading signs with wireless and electrical connection to display both open and closed status at four locations, and adding a fifth sign on Territorial Road west of Hwy 99E
  • Adding access to sign status through a phone app
  • Transitioning to fare collection by credit card instead of cash

Project map

Current activities

Installing fiber optic cable to the ferry signals. The fiber optic cable will be connected to the county’s fiber network sometime in July 2024. 

Schedule

  • Design: Dec. 2016 - March 2023
  • Right of way: April 2018 - June 2023
  • Construction: March 2023 - July 2024

Project impact on traffic

  • No road closures are expected during construction, although there may be delays up to 20 minutes near Advance Road or the ferry boat landings.

Funding

  • Estimated total project cost: $1 million 
  • Funded through federal Ferry Boat Discretionary Funds matched with county road funds
Contact Us
Department Staff
Joel Howie
Project Manager
503-742-4658
Sidebar Heading
Related Information
New Format?
On

Rural Curve Warning Sign Installation Project

Updated and enhanced curve warning signs will be installed on 18 rural county arterial and collector roads over 36 miles.

Status

Complete

Updated: April 4, 2023

These safety improvements are expected to provide:

  • 20–35% reduction in fatal and serious injury-causing crashes from adding curve warning signs 

The traffic safety team has assessed and determined proper curve advisory speeds to post along each road segment where curve warning signs will be installed along the following roads: 

  • 232nd Drive
  • Baker Road
  • Beavercreek Road
  • Borland Road
  • Elk Road
  • Feyrer Park Road
  • Grahams Ferry Road
  • Hayden Road
  • Knights Bridge Road
  • Ladd Hill Road
  • Leland Road
  • Lone Elder Road
  • Macksburg Road
  • Molalla Avenue
  • Rosemount Road
  • Tooze Road
  • Wilsonville Road

For more information on curve warning signs, read the ODOT Fact Sheet on Updated Curve Warning Signs

Why

To provide a safer roadway for all users and to reduce crashes.

Funding

  • Project estimate $250,000.
  • Funding is provided from county road funds and HB 2017 gas taxes. 
Sidebar Heading
Related Information
New Format?
Off

Radar Speed Sign Installation Project

Six radar speed feedback signs will be added to reduce the speed of travelers on Stafford Road, New Era Road and SE 282nd Ave. 

Status

Complete

Updated: Feb. 20, 2023

Radar signs will be installed at the following locations:

  • SW Stafford Road 
    • Northbound: south of SW Schatz Road
    • Southbound: south of Mountain Road
  • S New Era Road
    • Eastbound: west of S Central Point Road
    • Westbound: east Central Point Road 
  • SE 282nd Ave
    • Northbound: north of OR 212
    • Southbound: north of OR 212

Why

To provide a safer roadway for all users by reducing vehicle speeds.

Funding

  • Project estimate $500,000.
  • Funding is provided from county road funds.
Sidebar Heading
Related Information
New Format?
Off

Redland Road Radar Speed Sign Installation Project

Two radar speed feedback signs were added to reduce the speed of travelers on Redland Road approaching the community of Redland. An eastbound radar sign was installed near Norman Road and a westbound radar sign was installed near S Anna Mae Lane.

Status

completed

Updated: April 1, 2021

Why

To provide a safer roadway for all users by reducing vehicle speeds.

Funding

  • Project estimate $60,000.
  • Funding is provided from the County Road Fund.
Contact
Department Staff
Christian Snuffin
Project Manager
503-742-4716
Sidebar Heading
Related Information
New Format?
Off

242nd Ave/Borges Road Realignment

The intersection of SE 242nd Avenue and SE Borges Road is an intersection with high volumes of traffic crashes located in the Boring area. The project adjusted the intersection alignment and road grade. 

Status

Complete

Updated: Oct. 6, 2023

Construction plans Signing and striping plans

Why

To provide a safer roadway for all users and reduce traffic crashes and prevent vehicles from leaving the roadway at the intersection. 

Schedule

  • Design: Sept. 2019 - March 2021
  • Right of way: March 2019 - June 2019
  • Construction: Aug. 2023 - Oct. 2023

Funding

  • Project estimate $680,000
  • Funding is provided from Damascus Road Funds 

Other Resources

Contact
Department Staff
Mike Ward
Project Manager
503-742-4688

Sign Up For Email Updates

 
Sidebar Heading
Related Information
New Format?
On