Upper Kellogg Capital Improvements Projects (funded by American Rescue Plan Act (ARPA))

Status

Updated: March 11, 2026

WES’ construction contractor, Braun Construction, has completed the following:

  • Construction of new wetland at SE Tidwells Way.
  • Installed new storm system on Clackamas Road, which  included 14 storm catch basins, five storm manholes and 600 feet of storm pipe to help reduce flooding
  • Replaced 3 driveway culverts and restored habitats along Kellogg Creek
  • Finished the maintenance path on SE Tidwells Way.
     
  • Re-planted area with native trees and shrubs to bolster biodiversity and minimize maintenance efforts for years to come.
  • Constructed new maintenance/access path between SE Aldercrest Ct and SE Clackamas Rd., providing a better walking route to and from Ann-Toni Schreiber Park.


 

WES reduced flooding and improved habitat along Kellogg Creek (between SE Clackamas Road and SE Thiessen Road) by removing and/or replacing culverts and stream crossings as well as restoring Kellogg Creek.

Below is a detailed list of all activities that supported the restoration efforts of Upper Kellogg Creek. Each project is outlined in the Clackamas Water Environment Services (WES) Storm System Master Plan (SSMP), which details our approach for storm system infrastructure operations, maintenance and expansion with the goal of improving surface water quality and infrastructure within the WES service area.

For reference, a “culvert” is a device, usually a pipe or arched tunnel, that transports water underneath a road, railway, or other type of embankment.

(1) SE Clackamas Road Drainage Infrastructure 

Location: This project area is located west of where SE Clackamas Road crosses Kellogg Creek, southwest of Ann-Toni Schreiber Park.

Map of SE Clackamas Road Drainage Infrastructure
Figure 1: SE Clackamas Road Drainage Infrastructure (CIP 1091)

The opportunity: A stream drained into an undersized ditch inlet south of SE Tidwells Way. The excess water was collected by a standard ditch inlet at the edge of a residential property and transported by storm pipes down SE Clackamas Road directly into Kellogg Creek. The ditch inlet was not large enough to capture the stream flow, especially when debris collected at the inlet. The stream exceeded the capacity of the inlet and caused flooding on SE Clackamas Road and neighboring homes. 

The solution: 

  • Constructed and replaced approximately 600 lineal feet of 12 to 18-inch diameter storm drain in Clackamas Rd. and
  • Replaced drain and pond on SE Tidwells Way with 300 lineal feet constructed wetland and swale. 

(2) Aldercrest Culvert Replacement & Kellogg Creek Restoration

Location: The project area is located on Kellogg Creek, between SE Clackamas Road and SE Thiessen Road. 

Aldercrest Culvert Replacement & Kellogg Creek Restoration (CIP 1079)
Figure 2: Aldercrest Culvert Replacement & Kellogg Creek Restoration (CIP 1079)

The opportunity: The creek was confined and restricted by ten private driveway culverts and a concrete channel. Three of these driveways crossings used narrow culverts, resulting in streamflow backing up and exacerbating nuisance flooding on Clackamas Road. The creek also passed through a pair of parallel culverts, which are not associated with any crossing of the stream. These parallel culverts impeded natural stream flow. 

The solution: 

  • Removed culverts under three driveways and replace narrow stream crossing with a 20-foot span, three-sided concrete box culvert,
  • Restored 750 lineal feet of stream channel,
  • Removed invasive plant species and planted natives
  • Installed large wood structures to provide improved habitat in Upper Kellogg Creek. 

(3) Thiessen Culvert Replacement & Kellogg Creek Restoration

Location: The project area is located on SE Thiessen Road where it crosses Kellogg Creek, just west of SE Aldercrest Court. 

The opportunity: Kellogg Creek flows through an undersized (6-foot diameter) culvert which causes the creek to back up at SE Thiessen Road and flood the road and properties upstream. Due to the significant backwater caused by this culvert, the location was identified as one of the highest priority road crossing culvert replacements in the 2019 Upper Kellogg Basin Assessment prepared for WES. 

The solution: WES has partnered with Clackamas County’s Department of Transportation & Engineering (DTD) on this project; learn more about this project.

Contact
Department Staff
Leah Johanson
Senior Civil Engineer
503-502-4514

Phone:503-742-4567
Fax:503-742-4565

150 Beavercreek Road #430, Oregon City, OR 97045

Office Hours:

Monday - Thursday
7:30 a.m. – 5 p.m. 
Closed on the lunch hour 12 p.m. – 1 p.m.

Email:
Customer service
wescustomerservice@clackamas.us

Development services and permits
wes-permitservices@clackamas.us

Related Events
Water Environment Services
-