Clackamas County, Metro, community members and parks and recreation stakeholders joined forces to plan the future of Barton Park.
Clackamas County Parks teamed up with Metro and other key stakeholders to create a master plan that addresses public outdoor recreation needs for Barton Park and its associated properties. From expanding park amenities to easing the flow of traffic onsite and in surrounding areas, there are many changes in store that will benefit the community, neighborhood and park users.
Concept planning took place for three undeveloped sites totaling about 49 acres near Barton Park: Cazadero Natural Area, Barton Quarry and the Overlook property. The planning process, which was completed in summer 2020, will enhance the existing park to meet the needs of the public and ensure the undeveloped sites reflect community values.
Barton Park Complex Master Plan Draft Report: November 2020
Barton Park Complex Master Plan Draft Report Appendix: November 2020
About the Barton Park Complex
Barton Park is located on the Clackamas River just off of Highway 224, approximately four miles south of the unincorporated community of Boring. Barton Park is the largest and most popular county park, encompassing 122 acres and offering 112 campsites; 103 with water and electric hookups. Other park and recreational amenities include playground equipment, horseshoe pits, two volleyball courts, five picnic shelters, other picnic areas, a softball field and one boat ramp on the Clackamas River. Barton Park is a popular rafting destination due to its proximity to Portland and connection to the Carver Boat launch approximately six miles downstream.
Project Goals
- Develop a community-supported master plan that provides guidance for future expansion of Barton Park
- Prepare a master plan that strengthens the connection between Barton Park and Carver Park, and that integrates the disparate Barton Park Complex parcels of land
- Consider:
- Habitat conservation objectives and/or impacts
- The park’s designation as a Temporary Debris Storage and Reduction Site – an area designated to temporarily store, sort and manage debris following an event such as a wind storm, flooding or earthquake
- Functionality of the transportation system to and within Barton Park as well as traffic operations and intersection safety at key locations
- Connect Barton Park to the regional trail network and improve access to the future Cazadero Trail
Project Study Areas
Undeveloped sites to be planned
Summary of Community Input
From March-April 2020, we heard from nearly 400 people about their hopes and dreams for the future of Barton Park. Thank you to everyone who provided feedback in our online survey. Take a look at the results below.
Working Group
The Barton Park Master Plan Working Group guides the development of the master plan by providing technical guidance; reviewing and commenting on materials; and providing input on trailhead and park uses and layouts. The working group includes representatives from Metro, Oregon Parks and Recreation Department, the Eagle Creek Community Planning Organization, Clackamas County Pedestrian-Bikeway Advisory Committee, County Parks Board and other identified stakeholders.
Feb. 24, 2020 | Meeting #3 presentation |
Sept. 30, 2019 | Meeting #2 presentation |
May 15, 2019 | Meeting #1 context map complex map |