Project is in planning phase.
Updated: Aug. 1, 2024
Repairing erosion along the southern bridge support and embankment
During a routine bridge inspection, erosion was found at the southern support structure and along the slope near the Rainbow Road Bridge over Eagle Creek. We will repair the southern bridge support by installing large boulders and planting native vegetation.
Why
To repair erosion on the southern bridge supports.
Schedule
Work in the stream is required to be done between July 15-Aug. 31, 2025 to protect waterway species in Eagle Creek. Further details will be provided as they are known.
- Design: April 2024 to Dec. 2024
- Construction: Summer 2025
Traffic impact
Expect lane closures with delays up to 20 minutes. Work is expected to take one week to complete.
Current activities
- Project in design phase
- Coordinating permit applications of all required permits and approvals from local, state and federal regulatory agencies=
Funding
Funding provided by road funds.