Solar powered flashing lights may not always have enough power to operate reliably. We will connect the flashing sign to power utilities at this busy intersection.
Construction
Updated: April 1, 2024
Why
To maintain reliable operations, provide safer roadways for all users and to reduce maintenance costs.
Schedule
- Design: July 2023 – Jan.2024
- Construction: Jan. 2024 – Summer 2024
Traffic impact
Intermittent lane closures may occur during construction
Current activities
Project in construction phase.
Funding
- Project estimate $200,000.
- Funding is provided from a Community Development Block Grant and county road funds.