Project description
In construction
Updated: Feb. 4, 2025
Many portions of Monroe Street from Linwood Ave to Fuller Road have no sidewalks or bike lanes. This project will fill in those gaps and construct other improvements.
- On Monroe Street between Linwood Ave and Fuller Road the project will:
- Add 5-foot sidewalks to fill in gaps
- Add a 10-foot multi-use path (separated from traffic). (The path is proposed to be on the south side on the west section of Monroe and on the north side on the east section.)
- Upgrade curb ramps at intersections to comply with Americans with Disabilities Act (ADA) requirements
- Add landscaping strips
- Repair the road base, repave the road and improve the stormwater system
- A mini-roundabout at the intersection with 72nd Ave.
- On 72nd Ave between Monroe St and Thompson Road the project will:
- Add 5-foot sidewalks on the east side of street,
- Add a 10-foot multi-use path (separated from traffic) on the west side of street
- Add a landscaping strip on the west side of street..
- On Thompson Road between 72nd Ave and Lot Whitcomb Elementary School the project will:
- Add 5-foot sidewalks on the north side of street
- Add a 10-foot multi-use path (separated from traffic) on the south side of the street
- Upgrade curb ramps to ADA standards at intersections
Why
The improvements are designed to:
- increase safety and ease of access for motorists, bicyclists and pedestrians
- allow safer and easier access to schools and bus stops
- support healthy ways to commute to school and work
- support the community by making it easier and safer for residents to walk, bike, and enjoy their neighborhood
- reduce localized flooding and promote redevelopment
Schedule
- Design: Feb. 2021 – Dec. 2023
- Right of way: June 2023 – Nov 2024
- Construction: Winter 2025 – Spring 2026
Traffic impact
- Expect road closures with local access and emergency vehicles only.
- Expect a two-month road closure at Monroe St and 72nd Ave during summer 2025 to build the roundabout.
Things to be aware of
These improvements will complement other projects in the area including:
- Linwood Ave (Clackamas County) from Monroe St to Johnson Creek Blvd. Construction will start in late 2022 to create a bike/pedestrian connection to the Springwater Corridor.
- Linwood Ave (Milwaukie) from Harmony Road to Monroe St connects the west end of the Monroe St project to the Linwood Avenue Improvement Project at the Linwood/Monroe Intersection.
- Monroe St Neighborhood Greenway (Milwaukie) from 21st Ave to Linwood Ave.
Current activities
- Utility relocations
- Construction contractor chosen
- Construction in progress
Funding
- Estimated cost: $10.3 million
- Funding source: Clackamas County Development Agency through the North Clackamas Revitalization Area (NCRA) urban renewal district