Laurie Ave Stormwater Improvements

Status

Coordinating construction

Updated: Feb. 24, 2025

Extending Stormwater Infrastructure to Laurie Ave.

The project will install a new 12-inch diameter stormwater main on 436 feet of Laurie Avenue south of Courtney Ave and 6 catch basins to reduce the frequency of flooding. Additionally, 300 feet of stormwater main on Courtney Avenue west of Laurie Avenue will be replaced with 12-inch diameter stormwater pipe. 

Why

The new stormwater main and catch basins are expected to reduce flooding and convey a 10-year storm event.

Schedule

  • Design: June 2023 to April 2024
  • Construction: March 2025 to July 2025

Traffic impact

Construction is planned to start Monday, March 10, 2025. Expect delays on Laurie Ave and Courtney Ave between 7 a.m. and 6 p.m.

 

Current activities

Surveying and design services. 

Funding

  • Project estimate $800,000.
  • Funding is from county road funds.

Phone:503-742-4691
Email:engineering@clackamas.us

150 Beavercreek Road Room #325 Oregon City, OR 97045

Office Hours:

Monday to Thursday
8 a.m. to 4 p.m.

Available by phone/email
Friday
8 a.m. to 3 p.m.

Related Events
Transportation Engineering
-