In early 2021, heavy rains and strong winds caused fallen trees in Johnson Creek to damage the culvert supporting the road on Hideaway Court, in the Damascus and Boring areas. A temporary bridge is in use until the culvert can be replaced.
The culvert will be replaced with a bottomless culvert to allow for safe fish passage.
Design phase
Updated: March 17, 2023
Why
To preserve residential access.
Schedule
The county began the design phase in April 2021. Construction is planned between July and Aug. 2023, during daytime hours. Work will take up to 5 weeks to complete.
Traffic impacts
Single-lane closures will be needed during construction.
Current activities
Waiting for final design plans. Will send out construction bid by March 2023.
Funding
- Project estimate $950,000
- Funding is provided from Damascus County Road Funds