Project is in design phase.
Updated: Dec. 12, 2023
Many crashes occur on a windy segment of Canby-Marquam Hwy near Kraxberger Road (approximately between MP 5.05 and MP 5.45) due to drivers leaving the roadway, especially in wet conditions. Safety improvements include repaving to improve pavement friction, two radar-activated curve warning signs with lights, and enhanced safety signing.
Why
To increase safety and reduce lane departure crashes.
Schedule
- Design: Jan 2024 - Dec. 2024
- Construction: winter 2025/2026 - summer 2025
Traffic impact
- Intermittent lane closures will be needed during construction.
Current activities
- Project design
Funding
- Project estimate $470,000
- Funding is provided from HB 2017 state gas tax safety funds