Bear Creek Bridge Replacement and Molalla Ave Shoulders Improvement

County Roads Take Me Home stickerProjects funded through the new Community Road Fund will increase safety, relieve congestion and maintain local roads.

Project description

Status

Project planning.

Updated: Nov. 16, 2023

Although there are no immediate safety concerns related to the stability of the bridge or the roadway, the Bear Creek Bridge in the Molalla area is undersized. This project will replace the bridge and improve the roadside shoulders along S Molalla Ave from Sawtell Road to the Molalla City limits, just south of W 7th St. 

Why

To provide a safer bridge and roadway for all users. 

Schedule

  • Design: Sept. 2024 - Dec. 2025
  • Right of way: Fall 2024 - Fall 2025
  • Construction: Spring 2026 - Fall 2026

Traffic impact

  • A full road closure and detour is expected for the bridge replacement project during construction.

Current activities

  • No project activities are occurring at this time. 

Funding

  • Project estimate $1.85 million. 
  • Funding is provided from Community Road Funds and transportation system development charges. 
 
Contact
Department Staff
Jordan Cools
Project Manager
971-288-8136

Phone:503-742-4691
Email:engineering@clackamas.us

150 Beavercreek Road Room #325 Oregon City, OR 97045

Office Hours:

Monday to Thursday
8 a.m. to 4 p.m.

Available by phone/email
Friday
8 a.m. to 3 p.m.