Preparing for construction.
Updated: Nov. 4, 2024
Replace the damaged signal pole at the southwest corner of 82nd Dr and Jennifer St. Includes replacing all signal poles, adding mast arms and signal heads, repaving the intersection, reconstructing all curb ramps to meet ADA requirements and adding pedestrian push buttons.
Why
To maintain regional traffic signal connection and to improve pedestrian access.
Schedule
- Design: Sept 2023-winter 2024
- Construction: spring 2025- winter 2025
Current activities
- Selected DKS as the consultant for project design
Traffic impact
- Minor and intermittent lane closures for traffic signal upgrades will be needed.
Funding
- Project estimate $1.4 million
- Funding is provided from the county road funds