72nd / Luther Safety Improvements

Traffic engineers evaluated operations for vehicles, pedestrian and bicycles and identified low-cost improvements to reduce the number and severity of crashes at the intersection. The intersection will converted to an all-way stop. The intersection at Bell and Alberta will also be reconfigured.

Status

Complete

Updated: March 15, 2023

Why

To reduce crashes and improve safety for all roadway users.

Schedule

  • Design: July 2021 - Jan. 2023
  • Construction: March 2023 - May 2023

Funding

  • Project estimate $27,000.
  • Funding is provided from county road funds and HB2017 state gas taxes. 