Fischer’s Forest Park Septic System Update – Phase 2

Clackamas Water Environment Services (WES) owns and operates the Fischer’s Forest Park large onsite septic system (LOSS). The LOSS serves a community consisting of 26 homes on three cul-de-sac streets. 

Blue Lines: Existing Facilities, Green Lines: New Facilities, Red X’s: Facilities to Be Decomissions

Blue lines: existing facilities   
Green lines: new facilities   
Red X’s: facilities to be decomissions 

The original LOSS was installed in the early 1970s, and like any system that is 50 years old, even with routine maintenance, performance has deteriorate over time. Phase 2 will construct a new drainfield system, upgrade and relocate the treatment system to an area north of S Merry Meadow Ct, upgrade system controls and reliability, replace damaged concrete structures, and decommission the existing treatment system. Phase 2 will begin in June of 2023.

Fischer’s Forest Park LOSS History

The LOSS was initially built in the 1970s, consisting of three separate collection areas (East, Central and West), each with a septic tank and drain field. In the early 1980s, the drain field that serviced the West collection area began to fail. This unexpected system breakdown prompted a 1983 renovation of the system. The 1983 project made two major changes to the system.

First, instead of having separate drain fields for each collection area, the effluent from all three septic tanks was re-directed to a central recirculating tank. By combining the flows into one system, it would allow the updated facility to provide even dosing of the drain fields and help avoid overloading any one part of the system.

The second major change was the addition of a recirculating gravel filter. The filter served to further treat the wastewater, which in turn would limit the amount of solids being delivered to the drain fields. It was expected that wastewater with lower solids content would extend the life of the drain fields and decrease the likelihood of system issues in the future.

The system operated in that manner until 2006. In 2006, the recirculating gravel filter was replaced with a more modern filtration system, and a more sophisticated drain field dosing control system was installed. Outside of regular maintenance and equipment replacement, no upgrades or modifications have been done since 2006.
 

Project Background

Treatment pods

In 2019, WES hired consultants to complete an evaluation of the collection system (manholes, pipes, septic tanks, recirculation tanks, filtration units, etc.) and the drain fields.

The evaluations identified many deficiencies in the system:

  • Some of the pipes have developed sags, and there are areas where pipe connections have separated.
  • Several of the concrete structures have developed cracks, and while these cracks are not structural concerns, they let groundwater into the system, which can cause the system to exceed its treatment capacity.
  • Some locations where pipes enter the concrete structures have degraded, allowing groundwater into the system and can cause the system to exceed its treatment capacity.
  • Some of the concrete structures and cast iron pipes show signs of corrosion that could lead to structural failures if left unattended.
  • Damage caused by tree roots has left the central drain field severely damaged, and repairing the system in its current location is not a realistic option.
  • Evidence indicates the east and west drain fields are struggling and need to be rehabilitated or replaced.
  • The system’s operation and distribution controls are inefficient and should be modernized to improve the performance and life expectancy of the facility.

After receiving the results of the evaluation, WES hired a firm that specializes in septic design to develop a project to address the condition issues. Design work concluded in 2022. The new design will help ensure proper operation and durability for another 50 years. 

Construction work was separated into two phases. Phase 1 completed in Spring of 2023 and construction on Phase 2 will begin in June 2023.

Virtual neighborhood meeting on the Fischer's Forest Park large onsite septic system (LOSS).

Moving Forward

Construction will happen in two phases Phase 1 and Phase 2.

Phase 1 is substantially complete and included:

  • Replacing the entire gravity collection system, including manholes, mainlines, and residential service connections.

Phase 2 will begin in June of 2023 and will last approximately 3 months. Phase 2 includes:

  • Rehabilitate or replace septic tanks.
  • Make improvements to and move the treatment system to an area north of Merry Meadow court.
  • Create a new drain field over the area of the field that failed in the early 1980s.
  • Decommission the old treatment area. Decommissioning will consist of removing the fencing, fence posts (including concrete), filter pods, subsurface structures, and control panels. All holes will be filled with native material. The buried electrical conduit will remain but will be cut below the surface and capped.
  • Fencing: A permanent fence has been added to the project. Using a tractor to mow the field, as is done now, causes significant risk to the new system installed in the northwest portion of the property. It was determined that a fence or some other deterrent should be constructed. The new fence will have several gates so residents will have full access to the field. WES will take over maintenance of the area inside the fence. That maintenance will extend outside the fence to the north in order to maintain a walking path around the fenced area. 

Every effort will be made to make the construction activity as minimally disruptive as possible.

Contact
Department Staff
Nathan Seaver
Any questions or concerns can be sent to project lead
503-679-5709

Phone:503-742-4567
Fax:503-742-4565

150 Beavercreek Road #430, Oregon City, OR 97045

Office Hours:

Monday - Thursday
7:30 a.m. – 5 p.m. 
Closed on the lunch hour 12 p.m. – 1 p.m.

Email:
Customer service
wescustomerservice@clackamas.us

Development services and permits
wes-permitservices@clackamas.us

Related Events
Water Environment Services
-
Water Environment Services
-
Water Environment Services
-