Design phase.
Updated: Nov. 16, 2023
Extending Stormwater Infrastructure to Laurie Ave.
The project will install a new 12-inch diameter stormwater main on 436 feet of Laurie Avenue south of Courtney Ave and 6 catch basins to reduce the frequency of flooding. Additionally, 300 feet of stormwater main on Courtney Avenue west of Laurie Avenue will be replaced with 12-inch diameter stormwater pipe.
Why
The new stormwater main and catch basins are expected to reduce flooding and convey a 10-year storm event.
Schedule
- Design: June 2023 to April 2024
- Construction: May 2024 to Oct. 2024
Traffic impact
Expect delays on Laurie Ave and Courtney Ave during construction.
Current activities
Surveying and design services.
Funding
- Project estimate $800,000.
- Funding is from county road funds.